News & Events

August 12, 2009
Quarterly Report No. 2 - April -June 2009
[View PDF]

August 4, 2009
Canada Line Opening Day August 17, 2009
[View PDF]

July 23, 2009
YVR Construction Update #027
Emergency Ventilation System Testing at Sea Island Centre Station July 23, 2009
[View PDF]

July 21, 2009
Public Notice No. 158
Public Invited for a Sneak Peek of Vancouver City Centre Station on July 25, 2009
[View PDF]

View all News & Events


Home > About Construction and Traffic > Construction Updates & Project Information
 

Construction Information and Updates

Public Notices & Construction Updates
Restoration Bulletins
Restoration Public Notices
Information Bulletins
Monthly Construction Updates
Fact Sheets
Postcards
Letters
Overviews
中文譯本 (Chinese Translations)

Canada Line Cambie Street Restoration Map
Oakridge Business Area 39th - 43rd Ave Parking and Access Map (updated September 2008)
North Cambie Village Access and Parking Map (Updated September 2008)


Public Notices & Construction Updates
Vancouver

Use the filter function below to view Public Notices & Construction Updates by segment : (i.e. Downtown Vancouver, North Cambie, South Cambie)

Search by:        
Sorry, no documents match your search.

Additional Public Notices & Construction Updates:
2009
2008
2007
2006
2005

Richmond

Use the filter function below to view Public Notices & Construction Updates by segment : (i.e. Fraser River, Bridgeport, No. 3 Road North, No. 3 Road South)

Search by:        
Sorry, no documents match your search.

Additional Public Notices & Construction Updates:
2009
2008
2007
2006
2005

Sea Island

Additional Public Notices & Construction Updates:
2009
2008
2007
2006


Restoration Bulletins
August 4, 2009 Canada Line Opens on August 17, 2009
February 20, 2008 Restoration Bulletin No. 3 - Elevated Guideway Completion and Lane Restoration
November 21, 2007 Restoration Bulletin No. 2 - Road Openings & Street Restoration
October 26, 2007 Restoration Bulletin No. 1 - Cambie Heritage Boulevard Replanting

Restoration Public Notices
August 4, 2009 Canada Line Opens on August 17, 2009
July 13, 2009 Public Notice No. 156 Cambie Street Bridge Off-ramp Opens to Motorists
February 23, 2009 Public Notice No. 150 Traffic Lanes Restored on the West Side of Cambie Street at King Edward Avenue in Vancouver
February 16, 2009 Public Notice No. 149 Traffic Lanes on the East Side of Cambie Street at 29th Avenue Restored to Traffic
December 3, 2008 Public Notice No. 145 Traffic Lanes Restored on the East and West Sides of Cambie Street in Vancouver
June 11, 2008 Public Notice No. 137 Bridge Removal at Cambie Street and W. Broadway Begins This Weekend
May 8, 2008 Restoration Notice - East Side of Cambie Street between 43rd and 47th Avenue Reopens May 2008
January 30, 2008 Restoration Notice - Cambie Street From SW Marine Drive to 49th Avenue Area Re-opens to Traffic
January 17, 2008 Restoration Notice - East Side of Cambie Street Between 64th Avenue and 50th Avenue Scheduled to Re-open to Traffic
November 30, 2007 Restoration Notice - Traffic Restored in Cambie Village Area
November 16, 2007 Restoration Notice - Little Mountain Area of Cambie Street Scheduled to Re-open to Traffic in November

Information Bulletins
December 14, 2007 No. 19 - Branding of the Canada Line
October 3, 2007 No. 18 - Summary of the Vehicle Testing & Commissioning Phase
September 26, 2007 No. 17 - Canada Line's Commitment to Business Support
April 13, 2006 No. 16 - Final Project Report concludes Canada Line expected to deliver value for money
April 11, 2006 No. 15 - Public consultation continues for Canada Line
March 3, 2006 No. 14-Contract Confirms Public Protected From Potential Construction Cost Increases
January 16, 2006 No. 13-With Design Teams Selected, Station Design Consultations Begin January 2006
December 15, 2005 No. 12-Cambie Heritage Boulevard Update
December 7, 2005 No. 11-Working with Businesses - Liaison Committees Named
September 20, 2005 No. 10-RAV Line Design & Construction Update
August 2, 2005 No. 9-RAV Line Construction Phase Starts - RAVCO and InTransitBC Reach Final Agreement
July 14, 2005 No. 8-Airport Line Takes Shape - Decision on Project Options
June 30, 2005 No. 7-RAV Line Project Environmental Review Process Upheld in BC Supreme Court.
June 2, 2005 No. 6-Community Connections Canvass Underway
May 9, 2005 No. 5-Overview of RAV Line (Guideway, stations, construction and schedule)
April 22, 2005 No. 4-Further Assessment on two segments of the RAV Line by BC EAO
April 14, 2005 No. 3-RAV Workshop
April 8, 2005 No. 2-Addition of 2nd Avenue Station Supports Sustainable Development of Southeast False Creek
April 6, 2005 No. 1-RAVCO & InTransitBC (SNC-Lavalin/Serco) Reach Interim Agreement

Monthly Construction Updates
July 1, 2009 Monthly Update - Richmond and Sea Island: July 2009
July 1, 2009 Monthly Construction Update - Vancouver: July 2009
June 1, 2009 Monthly Construction Update - Vancouver: June 2009
June 1, 2009 Monthly Update - Richmond and Sea Island: June 2009
April 30, 2009 Monthly Update - Richmond and Sea Island: May 2009
April 30, 2009 Monthly Construction Update - Vancouver: May 2009
April 1, 2009 Monthly Update - Richmond and Sea Island: April 2009
April 1, 2009 Monthly Construction Update - Vancouver: April 2009
March 2, 2009 Monthly Construction Update - Vancouver: March 2009
March 2, 2009 Monthly Update - Richmond and Sea Island: March 2009
February 2, 2009 Monthly Update - Richmond and Sea Island: February 2009
February 2, 2009 Monthly Update - Vancouver: February 2009
January 1, 2009 Monthly Update - Richmond and Sea Island: January 2009
January 1, 2009 Monthly Update - Vancouver: January 2009
November 28, 2008 Monthly Update - Vancouver: December 2008
November 28, 2008 Monthly Update - Richmond/Sea Island: December 2008
October 31, 2008 Monthly Update - Vancouver: November 2008
October 29, 2008 Monthly Update - Richmond/Sea Island: November 2008
September 30, 2008 Monthly Update - Richmond/Sea Island: October 2008
September 30, 2008 Monthly Update - Vancouver: October 2008
August 28, 2008 Monthly Update - Richmond/Sea Island: September 2008
August 28, 2008 Monthly Update - Vancouver: September 2008
August 1, 2008 Monthly Update - Richmond/Sea Island: August 2008
August 1, 2008 Monthly Update - Vancouver: August 2008
June 27, 2008 Monthly Update - Richmond/Sea Island: July 2008
June 27, 2008 Monthly Update - Vancouver: July 2008
June 2, 2008 Monthly Update - Richmond and YVR: June 2008
June 2, 2008 Monthly Update - Vancouver: June 2008
May 1, 2008 Monthly Update - Richmond and YVR: May 2008
May 1, 2008 Monthly Update - Vancouver: May 2008
April 1, 2008 Monthly Update - Richmond and YVR: April 2008
April 1, 2008 Monthly Update - Vancouver: April 2008
March 17, 2008 Monthly Update - Richmond and YVR: March 2008
March 17, 2008 Monthly Update - Vancouver: March 2008
February 18, 2008 Monthly Update - Richmond and YVR: February 2008
February 18, 2008 Monthly Update - Vancouver: February 2008
January 4, 2008 Monthly Update - Vancouver: January 2008
January 4, 2008 Monthly Update - Richmond and YVR: January 2008
December 3, 2007 Monthly Update - Vancouver: December 2007
December 3, 2007 Monthly Update - Richmond and YVR: December 2007
November 1, 2007 Monthly Update - Vancouver: November 2007
November 1, 2007 Monthly Update - Richmond and YVR: November 2007
October 1, 2007 Monthly Update - Vancouver: October 2007
October 1, 2007 Monthly Update - Richmond and YVR: October 2007
September 4, 2007 Monthly Update - Vancouver: September 2007
September 4, 2007 Monthly Update - Richmond and YVR: September 2007
August 3, 2007 Monthly Update - Vancouver: August 2007
August 3, 2007 Monthly Update - Richmond and YVR: August 2007
July 3, 2007 Monthly Update - Vancouver: July 2007
July 3, 2007 Monthly Update - Richmond and YVR: July 2007
June 1, 2007 Monthly Update - Vancouver: June 2007
June 1, 2007 Monthly Update - Richmond and YVR: June 2007
May 1, 2007 Monthly Update - Vancouver: May 2007
May 1, 2007 Monthly Update - Richmond and YVR: May 2007
April 2, 2007 Monthly Update - Vancouver: April 2007
April 2, 2007 Monthly Update - Richmond and YVR: April 2007
March 2, 2007 Monthly Update - Vancouver: March 2007
March 2, 2007 Monthly Update - Richmond and YVR: March 2007
February 1, 2007 Monthly Update - Vancouver: February 2007
February 1, 2007 Monthly Update - Richmond and YVR: February 2007
January 2, 2007 Monthly Update - Vancouver: January 2007
January 2, 2007 Monthly Update - Richmond and YVR: January 2007
December 1, 2006 Monthly Update - Vancouver: December 2006
December 1, 2006 Monthly Update - Richmond and YVR: December 2006
View Archives (23)

Fact Sheets
August 24, 2007 No. 29: North Arm Bridge Construction
July 20, 2007 No. 28: Canada Line Construction Milestones
May 30, 2007 No. 27: Weld Plant and Track Installation Work
April 18, 2007 Canada Line Fun Sheet: Spring Edition
September 4, 2007 No 26: Canada Line Construction Quick Facts (Updated)
October 30, 2006 Canada Line Fun Sheet: Halloween Edition
October 16, 2006 No. 25: Elevated Guideway Construction
June 23, 2006 Canada Line Fun Fact Sheet: Summer Vacation Edition
Safety this Summer
June 10, 2006 No. 24: Canada Line’s Tunnel Boring Machine (TBM)
May 11, 2006 No. 23: Revision 2: Finding your way around the Canada Line
January 24, 2006 No. 22: Safety and Comfort on the Canada Line
January 24, 2006 No. 21: Linking buses to the Canada Line
January 30, 2006 No. 20: Yaletown Station & Entrance
December 15, 2005 No. 19: Guideway Alignment - No. 3 Road, Richmond
November 25, 2005 No. 18: The Canada Line Vehicle (Updated 12.14.07)
June 20, 2005 No. 17: Bored Tunnel Construction in Vancouver
June 20, 2005 No. 16: Protecting the Cambie Heritage Boulevard
May 14, 2007 No. 15: Construction Noise and Vibration in Richmond (Updated 05.14.07)
June 20, 2005 No. 14: RAV Construction in Richmond
June 20, 2005 No. 13: Dust and Emission Control - Richmond
June 20, 2005 No. 12: Traffic Management - Richmond
June 20, 2005 No. 8: revision 2: Air Quality and Dust Control
June 20, 2005 No. 7: revision 2: Construction Noise
June 20, 2005 No. 6: revision 2: Disposal of Surplus Excavated Materials
June 20, 2005 No. 5: revision 2: Community and Business Liaison
June 20, 2005 No. 4: revision 2: Traffic Management
April 5, 2005 No. 3: Environmental Management
March 1, 2005 No. 2: Acquiring the Right of Way
February 17, 2005 No. 1: Building the RAV Line - Vancouver Segment
View Archives (1)

Postcards
April 3, 2009 No. 51: LED the way in PIDs
March 6, 2009 No. 50: Brick by Brick
December 10, 2008 No. 49: Testing Testing Testing...
November 28, 2008 No. 48: Taking Shape
September 23, 2008 No. 47: Keeping Dry When it's Wet
September 2, 2008 No. 46: A Twist on Room and Board
June 2, 2008 No. 45: Train Testing - Grown up Style
February 1, 2008 No. 44: Restoring South Cambie
December 21, 2007 No 43: And then there were none
November 29, 2007 No. 42: Santa drops in on the Canada Line
September 17, 2007 No. 41: The North Arm Fraser River Bridge
June 22, 2007 No. 40: Paving Season Part 1 - Asphalt
June 15, 2007 No. 39: Tension on the Canada Line
May 14, 2007 No. 38: Up Up and Away
April 20, 2007 No. 37: Flash Butt Welding
April 13, 2007 No. 36: A tunnel is complete
March 21, 2007 No. 35: CANstruction - CANada Line Style
March 7, 2007 No. 34: Laying the Track
February 19, 2007 No. 33: A bit of a preview
February 9, 2007 No. 32: Making Headway
January 23, 2007 No. 31: Art
December 21, 2006 No. 30: Season's Greetings from the Canada Line Project Teams
December 20, 2006 No. 29: Closing the Gap
December 14, 2006 No. 28: Great "Potain"-tial
November 30, 2006 No. 27: Grounding the Canada Line at YVR
November 17, 2006 No. 26: Tourist Attractions - Canada Line Style
November 9, 2006 No. 25: Perfectly Balanced
October 27, 2006 No. 24: Rain Gear
October 12, 2006 No. 23: Bridge Works
September 22, 2006 No. 22: Threading the Needle
September 12, 2006 No. 21: Spanning the Works
August 31, 2006 No. 20: Canada Line Wildlife
August 25, 2006 No. 19: Tunneling Under False Creek
August 11, 2006 No. 18: Bridgeport's Really Big Machine
August 3, 3006 No. 17: Building Foundations for the Future
July 26, 2006 No. 16: Adding to the Landscape
July 17, 2006 No. 15: A Centrepiece - Canada Line Style
July 7, 2006 No. 14: Every Tunnel has a Top
June 21, 2006 No. 13: The "Heel For Heel and Toe For Toe" Approach
June 15, 2006 No. 12: The gentle giant gets ready to roll
June 1, 2006 No. 11: When is a bathtub not a bathtub?
May 26, 2006 No. 10: Safety First
May 12, 2005 No. 9: Planes, trains & automobiles
May 5, 2006 No. 8: The construction train is moving
View Archives (7)

Letters
January 11, 2007 Letter to North Cambie residents and businesses re: tunnel construction
June 12, 2006 Letter to Cambie Street Residents re: Notice of Condition Assessment Inspections
April 11, 2006 Letter to Little Mountain Residents re: Blasting
January 24, 2006 Letter to 1178 Hamilton Street re: Canada Line Preconstruction Condition Building Assessment
November 7, 2005 Letter to Little Mountain Area Residents re: Notice of Condition Assessment Inspections
April 22, 2005 Letter Regarding Further Assessment of the RAV Line
April 8, 2005 Letter to False Creek Residents
March 29, 2005 Letter to Corridor Residents

Overviews
August 4, 2009 Canada Line Opens on August 17, 2009
November 6, 2008 Canada Line Overview
March 23, 2007 Canada Line Overview
January 1, 2007 Canada Line Overview
August 1, 2006 Canada Line Overview
May 1, 2006 Canada Line Overview
February 1, 2006 Canada Line Overview
November 1, 2005 Canada Line Overview
November 1, 2005 RAV Line Construction Start Flyer
October 1, 2005 RAV Line Overview
February 1, 2005 About the RAV Line: Next Steps

中文譯本 (Chinese Translations)
July 1, 2006 Business Liaison Newsletter No. 2
May 1, 2006 Business Liaison Newsletter No. 1