Construction Methods

The Canada Line will be built using state-of-the-art construction methods. Once complete, the route will be almost 19 km long and will include an underground tunnel, an elevated guideway, two bridges and 16 stations.

The following section provides you with an overview of the construction methods being used to build the Canada Line, as well as their potential impacts. Construction activities include: